Posted on: August 23, 2018

Pavement Marking of Village Streets to begin Monday, August 27th

Pavement Marking

The 2018 Street Pavement Marking Program objective is to restripe all Village maintained streets this season. This project will be performed by Public Works Staff as time and weather allows during the hours of 7:30am – 2:30pm Monday - Friday.  Please be prepared for some delays when navigating throughout the Village while crews are working. The goals for the 2018 Program are listed below and will be completed in the following order:

  • Restripe center line markings (yellow) on Reinking Rd from Route 20 to Daniel Blvd
  • Restripe all Crosswalks and Stop Bars on collector roads starting closest to the Charter School first.
    • Wester Blvd
    • Cambridge Lakes Dr
    • Richard J Brown Blvd
    • Reinking Rd
  • Restripe all Neighborhood stop bars and crosswalks starting in oldest neighborhoods first.
  • Restripe parking lot at Baseball Complex and Skate Park parking lots